This map was created by a user. Learn how to create your own. This map shows a combination of political and physical features. It includes country boundaries, major cities, major mountains in shaded relief, ocean depth in blue color gradient, along with many other features. This is a great map for students, schools, offices and anywhere that a nice map of the world is needed for education, display or decor. Download Chennai Map apk 2.6x for Android. Chennai Map is the definitive map of your City, always at hand.
Phase 1 Information
Construction for Chennai Metro Phase 1 (45.1 km) started in April 2009, with the first section of the Blue Line (Line-1) between Koyambedu – Alandur opening in June 2015. Further sections opened up one after the other between 2015-2019, with the last section connecting AG-DMS to Washermenpet opening in February 2019.
In December 2015, a 9 km extension of the Blue line toward Wimco Nagar was approved at a cost of Rs. 3770 crore as part of the Phase 1 Extension project. Construction on this extension started in 2016-end and the line is expected to open for commercial operations in Q4 2020.
In 2019, Chennai Metro Rail Ltd. appointed Larsen & Toubro to create a feasibility report for extending Chennai Metro's Blue Line from the Airport to Kilambakkam. This proposed 15.3 km extension will have 13 elevated stations along GST Road and its Detailed Project Report (DPR) is expected to be ready by 2020-end.
Phase 1 Routes
This phase involves the construction of 2 new lines on standard gauge tracks:
Line-1 (Blue Line): Chennai Airport – Washermanpet (23.10 km)
- Status: Operational
- Type: Elevated & Underground
- Depot: Koyambedu (shared with Green Line)
- Number of Stations: 17
- Station Names: Chennai International Airport, Meenambakkam, Nanganallur Road (OTA), Alandur, Guindy, Little Mount, Saidapet, Nandanam, Teynampet, AG-DMS, Thousand Lights, LIC, Government Estate, Chennai Central, High Court, Mannadi, Washermanpet
Line-2 (Green Line): Chennai Central – St. Thomas Mount (22 km)
- Status: Operational
- Type: Elevated & Underground
- Depot: Koyambedu (shared with Blue Line)
- Number of Stations: 17
- Station Names: St. Thomas Mount, Alandur, Ekkattuthangal, Ashok Nagar, Vadapalani, Arumbakkam, CMBT, Koyambedu, Thirumangalam, Anna Nagar Tower, Anna Nagar East, Shenoy Nagar, Pachaiyappa's College, Kilpauk Medical College, Nehru Park, Egmore, Chennai Central
Phase 1 Route Map
The embedded map below shows the exact location of all stations and can be zoomed into!
An official PDF route map of Chennai Metro Phase 1 will be added here when available.
Key for map below: Phase 1 | Phase 1 Extension |Phase 2
Tenders
Chennai Metro (CMRL) Phase 1 tenders can be viewed on the CMRL's website. News on these notices, their bidders and contracts are covered in further detail on the news & construction page.
Maps Chennai India
List of Major Contractors
Contract | Contractor |
Detailed Project Report (DPR) Preparer and Interim Consultant till September 2014 | Delhi Metro Rail Corporation (DMRC) |
General Consultancy Services | Egis Rail – Egis India – Maunsell Consultants Asia – Balaji Rail Road Systems – Yachiyo Engineering JV |
168 Coaches (Rolling Stock) | Alstom India Ltd. |
Power Supply and Overhead Equipments (OHE), Signalling, Platform Screen doors and Tele-communications | Siemens AG – Siemens Ltd. |
Lifts and Escalators | SJEC Corporation – Johnson Lifts Pvt. Ltd. |
Design and Construction of Track Work in Viaduct, Tunnel, Underground and Depot in Corridor – I & II | Larsen & Toubro – Alstom Transport, SA – Alstom Projects India Ltd. |
Automatic Fare Collection (AFC) System | Nippon Signal Company Limited |
Design and build tunnel Ventilation System | Emirates Trading Agency – ETA Engineering Pvt. Ltd. |
Underground stations air conditioning system | Voltas Ltd. |
UAA-01: Construction of Washermenpet to Egmore/May Day Tunnels & 4 stations | Afcons – Transtonnelstroy JV |
UAA-02: Construction of May Day Park to AG-DMS Tunnels & 3 stations | Gammon – Mosmetrostroy jv |
UAA-03: Construction of AG-DMS to Saidapet Tunnels & 4 stations | Gammon – Mosmetrostroy jv |
UAA-04: Construction of Egmore t0 Shenoy Nagar Tunnels & 3 stations | L&T – SUCG JV |
UAA-05: Construction of Shenoy Nagar to Thirumangalam Tunnels & 4 stations | Afcons -Transtonnelstroy |
History: Key Dates of Phase 1
• 29 Jun 2015: Koyambedu – Alandur (Green line) – 10 km
• 21 Sept 2016: Airport – Little Mount (Blue Line) – 8.6 km
• 15 Oct 2016: Alandur – St. Thomas Mount (Green line) – 1.3 km
• 14 May 2017: Koyambedu – Nehru Park (Green line) – 8 km
• 25 May 2017: Little Mount – AG-DMS (Blue Line) – 4.8 km
• 25 May 2018: Nehru Park – Central (Green line) – 2.6 km
• 10 Feb 2019: AG-DMS – Washermenpet (Blue Line) – 9.8 km
Chennai Full Map Pdf Downloads
Click on ‘News & Construction Updates' below for project news, progress and updates.
Chennai Full Map Pdf Downloadable
Menu: News & Construction Updates | Overview | Phase 1 Info | Phase 1 Extension Info | Phase 2 Info | Metrolite Project Info
Chennai Map Pdf
Page last updated: July 19, 2020. Spot an issue? Let me know here.